Lexington UMC 2006 Habitat Build

Schedule and Reservations

Notice

The 2007 project is completed and the new owner is now occupying the new home. We are updating the software used to process this form. Please make no attempt to use this form while this notice is still on this web page. Until this software is updated (and until this notice is removed), this registration form will not be processed.

We hope to have this software updated before the end of the year (2007). We are sorry for any inconvenience.

Thanks,
Webmaster


All work to be performed by volunteers from the churches has been completed.

House Location: 337 E. Second Street
Project Dates: Aug 07 - Sep 15: See specific activities & work dates below.
Sep 17 - Sep 29: Contingency work dates (if required for weather delays, etc.)
Time: 8:00 - 3:30 each work day

Please fill out the following form: indicate your desired work schedule and click the [SUBMIT] button at the bottom to register your interest in this project. Required data in red.

Volunteer Name:
Street Address:
City: State: Zip:
Daytime Phone: Format: 859-223-4567
Evening Phone: Format: 859-223-4567
EMail:
Organization:

What would you like to do? When can you be there? We'll be doing these tasks on the dates noted. Just click the "checkbox" on the dates. No experience? Our Team Leaders will train you!

Volunteer tasks to be done        Completed tasks        Performed by "trade"

Note: Schedule last updated on 08.29.07 at 2:22pm.

MonTueWedThrFriSat
6 Aug 7 Aug
LAYOUT
Layout chalklines
Cut plates
8 Aug
OPEN
Layout day in case of rain
9 Aug
FRAMING 1
Walls/trusses
10 Aug
FRAMING 2
Deck, wdws, doors
11 Aug
FRAMING 3
Deck, wdws, doors
13 Aug
FRAMING
Punchout framing
14 Aug
FRAMING
Finish Framing
Plumbing; roofing
15 Aug
SIDING
Vinyl corners / starter
HVAC; plumbing; roofing
16 Aug
SIDING
Vinyl Trim
HVAC; electric
17 Aug
SIDING
Siding / metal
HVAC; electric
18 Aug
SIDING / EXT DETAILS
Railings; architectual details
Electric
20 Aug

Plumbing inspection;
HVAC inspection
21 Aug

Electrical Inspection
22 Aug 23 Aug

Framing inspection
24 Aug 25 Aug
INSULATION / SIDING
Insulate house; Miscl. projects
27 Aug

Drywall
28 Aug

Drywall
29 Aug

Drywall
30 Aug

Drywall
31 Aug

Drywall
1 Sep

Drywall
3 Sep
(Labor Day)
Drywall
4 Sep

Drywall
5 Sep

Vinyl Floor
6 Sep
TRIM / PAINT
Paint House
7 Sep
TRIM / PAINT
Doors; trim; paint
8 Sep
PAINT / CABINETS
Cabinets
10 Sep

Vinyl floor; finish mechanicals
11 Sep
MISC DETAILS
Door knobs, blinds
12 Sep
PAINT / CABINETS
Cabinets
13 Sep
OPEN
Carpet; shelving
14 Sep
LANDSCAPING
Hand grade yard; lay sod. Note:
5th 3rd Only
15 Sep
PUNCHLIST
Clean house; pressure wash
17 Sep
CONTINGENCY
Contingency
Squad
18 Sep
CONTINGENCY
Contingency
Squad
19 Sep
CONTINGENCY
Contingency
Squad
20 Sep
CONTINGENCY
Contingency
Squad
21 Sep
CONTINGENCY
Contingency
Squad
22 Sep
CONTINGENCY
Contingency
Squad
Comments for Volunteer Coordinator:

Your SECURITY CODE: Characters may be upper case or lower case!
Security Code
Can't read it? Refresh browser screen!
Enter Security Code Here:
  
  • All dates and tasks are subject to change depending on weather, volunteer numbers, trades work, lot conditions, etc.
  • Please come to the jobsite rain or shine, bring your own tools, and come prepared to do any task that may be required.
  • Lexington Habitat thanks you for your hard work and flexibility.